National field operations, installation pipeline and team intelligence.
| Availability | Workload | Quality | Safety | Speed | |
|---|---|---|---|---|---|
| Team Alpha | 62 | 92 | 94 | 98 | 88 |
| Team Bravo | 48 | 88 | 86 | 96 | 78 |
| Team Delta | 55 | 80 | 91 | 97 | 82 |
| Team North | 78 | 64 | 84 | 95 | 74 |
| Team Lagos | 70 | 72 | 90 | 98 | 85 |
3 projects in PH/Lagos stuck waiting for MPPT controllers — 9 days of slippage.
Action: Expedite supplier shipment from EPEver
Operating at 92% utilization — fatigue risk and quality dip likely next sprint.
Action: Reassign PRJ-1041 phase 2 to Team Bravo
Hospital install requires extra QA cycles before handover.
Action: Schedule joint walkthrough Friday
Maintenance tickets rose this week — driven by panel cleaning requests post-Harmattan.