Real-time command center for solar project health, dependencies, delays, procurement blockers, installation progress and handover readiness.
Sunrise Hospital cycle stalled — dependency to installation and handover.
Action: Approve Pylontech NG partial shipment
₦12.8M revenue at risk if procurement not unblocked within 48h.
PRJ-1041, PRJ-1045 and PRJ-1049 overlap weeks 27–28.
Action: Re-assign PRJ-1049 to Team Bravo
Mean cycle 71d vs 89d — review residential survey-to-install gap.
Handover may move forward to Wed; notify AlphaMart.
PRJ-1042 + PRJ-1045 if procurement approvals are cleared today.
| ID | Project | Client | City | Size | Value | Stage | Progress | Team | Deadline | Risk | Blocker | Next Action | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| PRJ-1041 | 15kVA Residential Solar Backup | BrightWay Homes | Abuja | 15 kVA | ₦8,500,000 | Installation | 62% | Team Alpha | 2026-07-10 | Low | — | Proceed to next stage | |
| PRJ-1042 | 50kVA Office Solar System | Oakfield Offices | Lagos | 50 kVA | ₦28,400,000 | Design | 28% | Team Bravo | 2026-08-21 | Medium | Design revision | Proceed to next stage | |
| PRJ-1043 | 120kVA Hospital Solar Infrastructure | Sunrise Hospital | Port Harcourt | 120 kVA | ₦76,900,000 | Procurement | 45% | Team Delta | 2026-09-30 | High | Battery shipment | Escalate procurement | |
| PRJ-1044 | 250kVA Factory Hybrid Solar | Northline Cold Storage | Kano | 250 kVA | ₦142,000,000 | Site Survey | 12% | Team North | 2026-11-15 | Medium | — | Proceed to next stage | |
| PRJ-1045 | 30kVA School Solar Upgrade | Holy Grace School | Ibadan | 30 kVA | ₦17,200,000 | Testing | 88% | Team Alpha | 2026-06-30 | Low | — | Proceed to next stage | |
| PRJ-1046 | 80kVA Retail Solar | AlphaMart Superstores | Lekki | 80 kVA | ₦41,500,000 | Handover | 96% | Team Lagos | 2026-06-01 | Low | — | Confirm handover |