Operations Command

Procurement Command Center

Pipeline, supplier scoreboard, spend analytics and approval queue.

Open Requests
14
In Transit
6
Awaiting Approval
3
Delivered (month)
42

Procurement Pipeline

Stage 1
Requested
₦12.4M · 12
Stage 2
Reviewed
₦8.2M · 8
Stage 3
Approved
₦18M · 6
Stage 4
Ordered
₦6.4M · 4
Stage 5
In Transit
₦11.8M · 6
Stage 6
Delivered
₦42M · 18

Supplier Performance Scoreboard

1
JA Solar NG
Panels · 14 orders YTD
94
On-time: 96%Quality: 98
2
Victron Africa
Inverters · 9 orders YTD
91
On-time: 92%Delay: 1.2d avg
3
Pylontech NG
Batteries · 7 orders YTD
78
On-time: 74%Delay: 4.2d avg
4
SolarRack NG
Mounting · 12 orders YTD
92
On-time: 94%
5
Cutix Cables
Cables · 22 orders YTD
88
Spend: ₦14M

Procurement Spend (₦M)

₦210M
YTD spend
₦18M
Pending PO
14%
MoM growth

Purchase Risk Alerts

  • Pylontech batteries 4.2-day average delay
  • MPPT controllers stock < 9-day cover
  • High-value PR-772 (₦24M) awaiting approval
  • PRJ-1043 hospital depends on this week's delivery

Pending Approvals

IDItemCostUrgency
PR-772Batteries x 12₦24,000,000
High
PR-774MPPT controllers x 15₦3,200,000
Critical
PR-775Monitoring gateways x 8₦2,400,000
Medium
Approve all 3 to release ₦29.6M and unblock 2 active installations.

Open Requests

IDItemProjectSupplierCostRequested byStatus
PR-770550W Solar Panel x 40PRJ-1043JA Solar NG₦18,000,000Grace Johnson
Approved
PR-77110kVA Hybrid Inverter x 4PRJ-1042Victron Africa₦6,400,000Grace Johnson
Ordered
PR-7725kWh LiFePO4 Battery x 12PRJ-1044Pylontech NG₦24,000,000Grace Johnson
Pending
PR-773Mounting Rails x 80PRJ-1045SolarRack NG₦1,240,000Grace Johnson
Delivered
AI Intelligence Feed
High
Switch battery supplier for next 30 days

Pylontech delays threaten PRJ-1043 handover; Felicity NG has 5-day shorter lead time.

Action: Issue trial PO with Felicity for 8 units

Medium
Consolidate cable orders

Combining next 3 requests with Cutix earns 6% volume discount.